Email:
Password:
Remember Me
Forgot your password?
Log in
New to Satt Academy?
Create an account
or
Log in with Google Account
Home
Ask Question?
Business Account
Exam
Exam List
Exam Result
Category
1-12 Class
Board Exam
Admission
Job Solution
Skill Development
Book Collection
Video Content
Blog Content
Question
Ask Question?
Current Affairs
All MCQ Question
All Written Question
Upload Question
General
Study Plan
Hand Note
Notice | News
Other
FAQ
Point
Package
Feedback
Home
Academy
Admission
Job Assistant
Current Affairs
Skill
Forum
Blog
Package
Unauthenticate
Guest
example@gmail.com
Login
Description
Home
Edit Description
Back
Edit Description
Fill up the form and submit
Question
A contractor employed 30 men to do a piece of work in 38 days. After 25 days , he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men?
1
1
1
4
1
3
4
1
1
2
ANSWER : 1
Descrption
<pre>remaining no of days = 38 - 25 = 13, the work was finished 1 day earlier. So 35 men can complete the work in 12 days <math xmlns = "http://www.w3.org/1998/Math/MathML"><mo>∴</mo></math> 1 ,, ,, ,, ,, <math xmlns = "http://www.w3.org/1998/Math/MathML"><mn>12</mn><mo>×</mo><mn>35</mn></math> <math xmlns = "http://www.w3.org/1998/Math/MathML"><mo>∴</mo></math> 30 ,, ,, ,, ,, <math xmlns = "http://www.w3.org/1998/Math/MathML"><mfrac><mstyle displaystyle = "true"><mn>12</mn><mo>×</mo><mn>35</mn></mstyle><mn>30</mn></mfrac></math> ,, = 14 days The contractor would bd (14 - 13) Or, 1 day behind. </pre>